After building the Vanguard-class submarines, Britain waited years before starting work on the Astute class. A RAND study published in 2011 found that in this gap, “submarine design and build skills atrophied in the United Kingdom.” Many skilled designers and builders were reaching retirement age.
The Ministry of Defence brought in advice from the American shipbuilder General Dynamics Electric Boat. In 2009, a parliamentary committee reported that the program was 57 months late and 53 percent over budget.