Still Achievable

Crossrail, the new railway across London, was due to open in December 2018. In March 2018, the company’s position was that December 2018 was “still achievable, but increasingly challenging.” In August 2018, Crossrail Ltd announced that “the programme could not be delivered on time.”

In 2019, a London Assembly committee found: “Significant concerns raised by the independent reviewer, as early as January 2018, were largely ignored.”

understand-culture
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.