The Northridge earthquake of 1994 brought down sections of the Santa Monica Freeway in Los Angeles. The rebuilding contract gave the contractor, C. C. Myers, 140 days, and a bonus of $200,000 for each day the bridge opened before the deadline.
Myers finished in 66 days, 74 days ahead of schedule. The bonus came to about $14.8 million. Some reports gave $14.5 million.