The Santa Monica Freeway

The Northridge earthquake of 1994 brought down sections of the Santa Monica Freeway in Los Angeles. The rebuilding contract gave the contractor, C. C. Myers, 140 days, and a bonus of $200,000 for each day the bridge opened before the deadline.

Myers finished in 66 days, 74 days ahead of schedule. The bonus came to about $14.8 million. Some reports gave $14.5 million.

understand-culture
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.