The modernization of Line 1 of the Mexico City Metro was scheduled to run from July 2022 to March 2023. The section from Pantitlán to Salto del Agua was to reopen to passengers in March. In February, the authorities moved the date to May. The May date also passed.
Expansión reported in August 2023 that Martí Batres, the head of the city government, would not give a new date: “Ya no estamos lejos, pero no te pongo una fecha precisa” (We are not far now, but I will not give a precise date).